Bow Mar publishes a clear two-step sequence: applicable Design Review Board approval first, then the Town building-permit process. The owner should plan around a monthly DRB calendar, document completeness, approval expiration, contractor licensing, construction-plan requirements, and separate driveway or street-cut review.

Current reviewSources checked August 22, 2026Next scheduled review November 15, 2026
Return to the maintained online record

Authority path

Who may review the project?

Which Design Review Board application, Town permit, fire, water and sanitation, driveway, and private-property obligations apply?

First approval
Town of Bow Mar Design Review BoardThe applicable DRB application and complete exterior package precede the building-permit step.
Building permits
Town of Bow Mar Building DepartmentThe Town administers permits, contractor licensing, plan review, and inspections through the published Bow Mar process.
Access and public work
Town Public Works CommissionerStreet cuts and qualifying driveway or culvert work use a separate application and review path.
Fire and utilities
South Metro Fire Rescue and serving districtsConfirm fire, water, sanitation, and utility requirements for the exact improvement and parcel.

Current local signals

What changed—or deserves attention now?

Monthly · Decision calendar

The DRB meets on the second Tuesday with an advance cutoff.

The Town states that a complete application is due by the 24th of the preceding month and that the homeowner must attend the meeting. DRB approval is valid for 180 days.

Current · Approval clock

Design approval and building permits have different validity periods.

DRB approval is published as valid for 180 days, while Bow Mar building permits are published as valid for 360 days. These clocks should appear in the owner schedule.

Owner decision matrix

What should be verified before design or pricing commitments?

ScopeTrigger to verifyStarting authoritiesEvidence to assemble
Pool, spa, or water environmentExterior property change, pool and barrier work, utilities, drainage, landscape, driveway, or fire review.Applicable DRB first; Town building and trade permits; fire and utility providers as applicable.Complete exterior plan, survey or plot plan, pool and equipment, barriers, utilities, drainage, landscape, lighting, access, and materials.
Pavilion, pool house, or four-season roomNew structure, addition, remodel, exterior change, kitchen, bathroom, structure, or MEP work.DRB before Town building permit; fire and utility review as applicable.Correct application, scaled plot and floor plans, roof plan, four elevations, colors and materials, structure, landscape/civil, MEP, soils report, and schedule.
Outdoor kitchen or fire featureGeneral property change, structure, gas, electrical, plumbing, fire, lighting, or landscape impact.Applicable DRB; Town building and trade review; South Metro Fire as applicable.Location, materials, appliances, fuel and shutoff, loads, clearances, lighting, drainage, screening, landscape, and service access.
Retaining, grading, or drainageChanged contours, runoff, walls, structural work, landscape/civil scope, or driveway drainage.DRB and Town building review; Public Works for driveway, culvert, street cut, or right-of-way work.Scaled plot plan with existing and proposed contours and runoff, wall geometry, structure, soils, drainage, driveway interface, and restoration.
Landscape, irrigation, or hardscapeLandscape change, general property change, exterior composition, runoff, lighting, or driveway work.DRB using the applicable landscape or property-change application; Town and utility review as needed.Landscape plan, removals and protection, irrigation, materials, grades and runoff, lighting, privacy, utilities, construction access, and establishment plan.
Driveway, street cut, or stagingRoad cut, driveway repair or replacement involving culvert or drainage, right-of-way work, or construction logistics.Town Public Works Commissioner; DRB and building review where the work is part of the larger project.Application, driveway and drainage plan, culvert, street restoration, utilities, access, staging, schedule, and up to 20 days of published processing time.

Official starting points

Sources supporting this planning record

  1. Design Review Board ApplicationTown of Bow Mar · Supports: Application types, scaled-document requirements, meeting and submittal calendar, homeowner attendance, and 180-day approval validity.Checked August 22, 2026
  2. Building ProceduresTown of Bow Mar · Supports: Two-step approval sequence, contractor licensing, required construction documents, soils report, inspections, and 360-day building-permit validity.Checked August 22, 2026
  3. Street Cut & Driveway PermitsTown of Bow Mar · Supports: Separate street-cut, qualifying driveway and drainage permit path and the Town’s published allowance of up to 20 days for processing.Checked August 22, 2026
  4. Construction and Community Risk ReductionSouth Metro Fire Rescue · Supports: The fire-authority starting point; verify the property and exact fire, access, and water-supply scope.Checked August 22, 2026